Lillifield Bushfire Resilience Project Plan

This project received grant funding from the Australian Government.

Follow the Project step by step.

MILESTONE 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 

australian-government-stacked-black_168791ec-96ad-3bcc-817b-27e71beb4522....png

✔ MILESTONE N°1: Project Set-Up
Preliminary consultation and project administrative implementation.

DUE DATE: 29.05.22           COMPLETION DATE: 16.05.22 âœ”

Milestone1

MILESTONE N°2: Fire Response Unit & Shed
Fire response unit completion, procurement of equipment, installation of fixtures and fittings.

DUE DATE: 14.08.22           COMPLETION DATE: TBA

(delayed due to the floods)

Milestone2

MILESTONE N°3: Water Tanks
Purchase and installation of water tanks/hydrant system.

DUE DATE: 29.07.22           COMPLETION DATE: TBA

Milestone3

✔ MILESTONE N°4: First Aid Course
Completion of First Aid course, workshop preparation, advertising and evaluation.

DUE DATE: 28.08.22           COMPLETION DATE: 13.08.22 âœ”

✔ MILESTONE N°5
“Get Ready” fire safety workshop: book, prepare, advertise and evaluate workshop.

DUE DATE: 29.10.22           COMPLETION DATE: 04.09.22 âœ”

Fire-Ready-WORKSHOP.png
Milestone-5-Bushfire-resilienceProject.png
Milestone4
Milestone5

MILESTONE N°6: Fuel Load Reduction
Land management: report on high-risk areas, engage bush-regeneration and machinery contractors.

DUE DATE: 29.12.22           COMPLETION DATE: TBA

Milestone6

MILESTONE N°7: Community Centre Sprinkler System
Complete community centre bushfire sprinkler system.

DUE DATE: 31.10.23           COMPLETION DATE: TBA 

Milestone7

MILESTONE N°8: Project Completion
Set ongoing maintenance program for Lillifield fire prevention working bees. Project acquittal.

DUE DATE: 31.03.24           COMPLETION DATE: TBA